PUBLIC RESTROOMS 4: Planning intern Jorge Mata compresses the layer of aggregate surrounding the pipes In preparation for the concrete pour. [Photo & text: sa]


Heating coils are layed out and the exposed pipes are wrapped in protective foam. [Photo & text: sa]


With help of a lot of people the long pump hose was carried down from the third level to this location. The pour begins. [Photo & text: sa]


Ron Chandler guides the pump hose at one end, while screeding commences at the other. This floor is difficult to finish, as it needs to gently slope towards the drains. [Photo & text: sa]


Furious activity, in costume no less. The concrete pour continues in a third location, the footings for the solar panel installation behind the
East Crescent Complex. The report of that will post on 6/10. [Photo & text: sa]


An elevated set of crossbeams gives access to the finishing crew. [Photo & text: sa]


The floor is finished. Next step in this location will be the framing of the walls. To be continued. [Photo & text: sa]