A crew from BACDON FLOORS in Camp Verde mixes gypcrete for three rooms on the second floor of the East Crescent complex.
[Photo: Haley Byrd & Text: sa]



?

The soupy gypcrete is pumped to the second floor. Note the elevated rubber boots to protect the hydronic system.
[Photo: Haley Byrd & Text: sa]



?

Floors were finished in the main rooms of Unit 6 and Unit 7 and in the light-scoop apartment of Unit 7.
[Photo & Text: sa]



?

The main room in Unit 7 will be a classroom. Here are the connections to the main solar panel behind the Crescent and its storage batteries. Plumbing, ducts and the hydronic system control are left exposed for future class instruction in solar system set-up and utilities.
[Photo & Text: sa]